Unpacked

Lucy. Construction Updates





Markets: Austin

Things are moving right along as we work on building Lucy!


Come here to watch the paint dry:

4/6/21

What’s up at Lucy? Your update awaits:

Lucy construction has pushed on at a good pace.

  • Phase 1 homes: insulation and drywall installation.
  • Phase 2 homes: framing continues.
  • Phase 3 homes: foundations poured.
  • Phase 4 homes: pinning finished, vertical construction beginning. 

Coming up next: Pool excavation and construction.

Need a break? Come and drive past – things are looking great!


2/28/21

Let’s check in with Lucy – this month we have a special anecdote:

“After winter storm Irma, our concrete contractor told us that StoryBuilt was the only builder able to pour foundations the Monday following due to the quality of below slab vapor barriers that StoryBuilt directed their trade to use in lieu of less-expensive alternatives. Every other builder had to re-do their wraps because they did not withstand the harsh weather over the course of the week.”
– Hank Parker, Development Manager

  • Phase 1 – framing and trimming work
  • Phase 2 – foundations poured with framing begun.
  • The detention pond has fencing completed
  • Pool lot ready for excavation

 Up next: Phase 3 starts  Catch you back here next month!


1/31/21

Lucy, you’re looking good! Let’s check in:

  • Horizontal construction is nearly done – our road is paved.
  • First phase home foundations are poured.
  • First phase home framing starting up.

Coming up – Next phase foundations.

See you here next month!


12/31/20

Fa la la la Lucy! Let’s see what’s up!

  • Horizontal construction is nearly done – our road is paved.
  • First phase home foundations are poured.
  • First phase home framing starting up.

Coming up – Next phase foundations.

See you here next month!


11/30/20

Horizontal Construction was key this month – let’s get into it! 

  • Perimeter concrete wall nearing completion.
  • First phase of home foundations ready to pour next week.
  • Road paving to be largely complete in the next 2 weeks. 

Important: One home is unsold. Grab your bff and turn them into your neighbor.

See you next month!


10/28/20

Whoooo, Lucy! Things are hopping at the site:

  • Lots of progress in horizontal construction
  • Perimeter concrete walls construction started
  • Utility tie-ins happening at 12th street
  • Preparing subgrading for road paving

Something else big – we’ve sold 26/27 homes. We are so excited for this village to come to life – more updates next month!


9/18/20

  • Utility work is continuing
  • Detention pond completed
  • Wet utilities to be tied in to city services by end of month.
  • Electric utilities nearing completion
  • Construction dirt is being hauled away
  • Lots of progress in horizontal construction on-site
  • 22 out of 27 homes sold. Can’t wait for you all to meet your new neighbors!