Unpacked

North Bluff 3 Construction Updates





Markets: Austin

What’s going on at North Bluff 3? This is where you can find out!


Come here to watch the paint dry:

4/6/21

North Bluff, what’s going on? Let’s see:

Block 1 Townhomes are drywalled, cabinets hung, and getting close to end of construction.

Other areas: 

  • Phase 4 is in vertical construction.
  • Mail kiosk flatwork poured.

Coming up this month: 

  • Phase 5 foundations pouring soon. 
  • Single family (near Block 1 townhomes) units drywall starting.
  • Mailbox installation.

We’re glad to see all the progress. Check back here next month!


2/28/21

Excellent progress has been made onsite, with our first phase of homes. Let’s see what’s going on at North Bluff.

  • Townhome block 1 – drywall installation starting.
  • The dividing fence complete, along with our new fence at the south end of the site-both look great. 
  • Phase 4 single-family homes have their forms set up and will be pouring foundations soon. 

Next up is Phase 5 –  we expect to start pinning, staking, and forming foundations shortly after Phase 4 foundation pours.

Meet you back here next month!


1/31/21

Things are hopping at North Bluff 3. Let’s dig in:

  • Townhome #1: Drywall starting up.
  • Townhome #2: Framing finishing up.

Single-Family Residences:

  • Mechanical work ongoing.
  • Electrical work ongoing.
  • Plumbing work ongoing.

The days are getting longer here at North Bluff. Come back and check in with us next month!


12/31/20

What’s going on at North Bluff 3? You came to the right place, friend. Buckle up.

  • Foundations poured for homes 82-85, 98,99, and townhome block 2.
  • Townhome block 1 siding is going up.
  • Framing start for homes 82-85.

North Bluff 3 is sold out. We are ready for the new year!

See you here in 2021!


11/30/20

What’s going on at North Bluff 3? You came to the right place, friend. Buckle up.

  • Four new home foundations poured.
  • First block – installing doors and windows.
  • Concrete site wall completion in 2 weeks. 
  • Perimeter cedar fence ready to start.

There are only 2 homes left. Both are D plans – 2 br / 2.5 ba / 1590 sq. ft. Tell your friends and get ready to be best neighbors.

See you back here next month!


10/28/20

North Bluff 3 – it’s happeniiinnng –  we are moving right along and it’s good to see!
This just in:

  • Forms are being set for perimeter wall dividing NB3 and Capitol Chevrolet
  • Continued vertical construction on Townhome Block 1 and have topped out framing to the third level
  • Phase 2 of construction will begin with foundation forms set in the next three weeks
  • Sidewalk in right of way was poured and inspected

Meet you here next month.


9/16/20

The Latest on North Bluff 3 has a LOT going on:

  • Land development very close to completion.
  • We’re at 30/33 homes sold! One E plan and two D plans are left. 
  • Townhome block 1 framing underway.
  • Vertical construction on Townhome Block 2 started and and first two floors of framing are complete.
  • All team members met onsite to discuss and review progress. 
  • Sidewalk in right of way has forms set up and will be poured in the next week.