Unpacked

Luma Construction Updates


What’s going on at Luma? This is where you can find out!


Come here to watch the paint dry:

8/16/21

I’m gonna level with you, Luma.

You’ve got building 7 completed with 2 units closed, another on the way this month, and a 4th unit soon to come in September. A paint wall-out trim installation is underway this week for building 4, while building 5 is getting inspected for pre-insulation, and movement on roof decking for building 6 is ongoing.

That’s all for now. Someone leave the light on for Luma.


7/21/21

Luma’s been busy so let’s dive in.

This week we have a few more polishings and NHPs on units 702 & 703 in Building 7. We’ll have Building 4 textured with tape & float by the end of this week. Building 5 will transition to drywall by mid-August and we’re in the middle of decking and sheeting the exterior for Building 6. That should be achieved within the next few weeks. 

Hang in there, Luma!


6/15/21

Moving right along at Luma. What’s been going on? Let’s check.

  • Building 4: Getting inspections in place to start drywall.
  • Building 5: Framing the roof.
  • Building 6: Framing 3rd floor and roof.
  • Building 7: Interior and exterior finishes.

We’ll meet you back here next month!


5/14/21

Things are good at Luma in May. Let’s check in:

  • Building 3: Working on finishing inside and working on sidewalks and exterior landscaping.
  • Building 4: Wrapping up rough framing.
  • Building 5: Starting framing.
  • Building 6: Working on foundation – 4 pours to complete, second pour delayed due to rain.
  • Building 7: Working on trim and doors.
  • Building 8: Units 801 – 803 Specs and finishing paint.

See you back here next month!


4/21/21

It’s good to see Luma looking so great. Let’s check in! 

  • Building 3: 301-305 complete.
  • Building 4: Working on cornice. 
  • Building 5: Working on first floor framing.
  • Building 6: 601 foundation pour. 606 framing start. 
  • Building 8: Final paint touchups in units. Preparing for new home presentations.
  • Building 9: Final touchups and cleaning.

See you back here next month.


2/28/21

Hey, Luma, what’s up? Now that the snow’s gone, let’s check in: 

  • Building 3: Working on final paint and touch ups for walkthroughs in March.
  • Building 4: Working on frame rough-ins. 
  • Building 5:  Working on frame rough-ins.
  • Building 6: Foundation pours. 
  • Building 7: Tiling and exterior siding work.
  • Building 8: Units 801, 802, 803 have final paint work coming up.
  • Building 9: Units 904/905 are in finishing touches and nearly move-in ready.

It was a busy month, for sure. We’ll see you back here for next month’s update!


1/31/21

New year, new Luma news! Let’s check in:

  • Building 3: Inside finishing work. Outside work on sidewalks and landscaping. 
  • Building 4: Finishing up rough framing. 
  • Building 5: Framing is starting.
  • Building 6: Foundation pouring underway. 
  • Building 7: Work on doors and trim.
  • Building 8: Finishing paint.

Blue skies today at Luma. Meet us back here next month. 


11/30/20

So much going on at Luma. Let’s get into it!

Building 8: Finishing touches going in – flooring, trim, electrical trim out work (light fixtures, wall outlets, switches and cover plates.)

Building 3: 301 – 305 Tile Work

Building 4 & 5: Framing Start

Building 7: Weatherproofing wrap going up. Inspection next up. 

Lots of careful work and big steps going on here. Meet us next month for more in the continuing story of Luma.


9/17/20

Unit updates by number. Lots going on and we’re happy to let you know what’s up!

  • 301 – 305: Finishing hanging drywall this week, starting tape & floating and should texture by the end of next week. Interior trim to follow. Paint and cabinets to follow by mid October.
  • 401 – 402: Setting form boards today, call for form survey next week and plumbing rough install.
  • 501 – 504: Setting form boards today, call for form survey next week and plumbing rough install.
  • 701 – 705: Finishing mechanical roughing in, starting frame punch next week: coming up – frame inspection and start insulation poly and foam.
  • 801 – 806: Installed interior trim, cabinets and garage doors. Interior wall out next week, tile to start 1st of October.
  • 901 – 906: Electric meters installed, interior trim painted, A/C units started, wood flooring finishing up, drywall punch starting, final paint starting next week, install decks starting today, Landscaping starting 10/1, appliances 10/5.