What’s going on at Ruby? This is where you can find out!


Come here to watch the paint dry:

October 2022

What’s going on at Ruby? You’ve come to the right place.

We got our pre-walk checklist items are submitted to the city and waited on the city inspector to sign off on the project – success! We were then able to submit for final plat.

The alleyway is in.

Ongoing work on house pads and electrical utilities.

Meet us here next time for Ruby news.


September 2022

Standing by for a delivery window on concrete but beyond that, Ruby’s alley is formed and all steel is in place. Also happy to report that engineer and city inspections have both passed.

Way to go, Ruby!


July 2022

Hi Ruby! We’ve got good news – let’s dive in.

  • We were granted our extension by the city of Plano and the historic district. This is excellent.
  • Underway: Working on alleyway and house pads.
  • Up Next: We’ve got our eyes on mid-August for horizontal development completion.

Let’s talk soon – see you back here next month!


June 2022

Heyyyyy, Ruby, time for update numero dos! 

Excavation and subgrade prep for the alley is underway. Alley concrete paving to follow, with final plat after that. 

Vertical (you heard us) permit submittal is in plan check with City of Plano Building Department. Purchasing for vertical construction is coming up now that the bid set is available. 

Enjoy the last of your fully horizontal days, Ruby. Vertical is coming atcha. See you next month!


May 2022

Hey Ruby, let’s get this started!

We’ve officially picked up the plan sets from our Dallas office and delivered them to the city for permitting.

This is our first Ruby update. Come back next month and find out what’s been going on. We’re glad to have you on board.