March – May 2023

Hi Stanley fans, we’re here with a spring update: let’s look at what happened from March, April, and May.

Stanley is new construction townhomes in Seattle’s Georgetown, and things are looking good.

  • Building 1: MEP inspections completed. Completed hardwood flooring, cabinet, and countertop installation. Bathroom tile and kitchen tile installation started.
  • Building 2: Completed electrical rough-in. Completed insulation, drywall installation, and insulation and framing inspection.
  • Around Stanley: Bike shed slab poured. Exterior painting and siding underway.

We’ll see you back here for Stanley’s next update.


January 2023

Georgetown’s Stanley is moving right along as the days get longer. Sure it snowed a few times, but we know March is coming.

  • Building 1: Electrical rough in and inspection complete. Siding is finished.
  • Building 2: Plumbing rough in complete, with HVAC and electrical happening now.

Let’s meet back here next month.


December 2022

Stanley, you’re looking good, and we love that for you. November and December is a cold, dark time in Seattle, but we handled it together and it’s now light at 5 pm. That’s good news in new construction.

Let’s check in:

  • Building 1: The site work contractor is working on digging the Building 1 electrical secondary trenching. Windows and exterior doors have been delivered. Plumbing rough in is complete, HVAC rough in is 80% complete, and electrical rough in is 25% complete. The electricians will begin pulling wire shortly. Building 1 roof and deck membrane are nearly complete. Weather resistant barrier is 80% installed.
  • Building 2: Framing is complete, with some pick up work and unit 14 second and third floors. Roof vapor barrier is installed. TPO roof membrane will be installed as weather allows. Windows are being installed and plumbers have begun rough in.

See you back here next time, Stanley fans!


October 2022

Hi Stanley, looking sharp! Let’s get into it.

  • Building 1: Temperature roof/vapor barrier installed, windows and building wrap starting up. MEP (mechanical, engineering, plumbing) trades completing exterior penetrations and beginning MEP rough in.
  • Building 2: Nearly topped out, only penthouse stair rooms remain.

The cake shop – Deep Sea Sugar and Salt – across the street is very popular. We’re here to give you news you can use. See you back here soon.


September 2022

Foundation drainage and backfill are ongoing but below grade weatherproofing has been finalized. Where walls are concerned, 1st floor walls are being setup on building 1 and building 2’s walls are prepped, just two days behind building 1 before they’ll be put up. Foundation mat slabs on both buildings are all done.

Thanks and we’ll catch ya next time!