Unpacked

Frank. West Construction Updates





Markets: Austin

What’s going on at Frank. West? This is where you can find out!


Come here to watch the paint dry:

1/31/21

Lots of things going on Frank West. Let’s dig in:

  • Unit 5: Tub installs, sliding doors coming up. 
  • Unit 6: Window installs, concrete prep for piers.
  • Unit 9: Trim installs, painting, finishing wall tile.
  • Unit 10: Flooring installation coming up.
  • Unit 11: Appliances and flooring installation.
  • Unit 12: Closet installation, cedar for back porch coming up. 
  • Unit 13: Closet installation, flooring coming up.  
  • Unit 14: Closet installation, flooring coming up.  
  • Unit 15: Brick cleaning, ac pad concrete pouring.
  • Unit 16: Mech trims continuing, rough final grade completion coming up.
  • Unit 17: Plumbing and electrical set out in progress. Rough final grade complete.
  • Unit 24: Tile punch and wood floor punch being completed, exterior painting coming up.
  • Unit 26: 2/1 – Gas meter inspection this week, scheduling final inspections.

We’ll see you back here next month. Happy New Year!


9/17/20

Right now:

  • Construction remobilized on townhome units, with anticipated completion of units 29 and 30 this month.
  • Site clean up.
  • Common area landscaping around townhome units.
  • Common area landscaping site walls are being formed/poured for community walking path.

Coming up next!

  • Anticipated completion of remaining townhome units 24-27.
  • Construction remobilization on single-family units 5-17.
  • Completion of carports for townhomes and single-family homes under construction.
  • Continued work on common area landscaping.