7/29/20

What’s been going on since our last update at the end of May? A lot. Willa’s sales have been heating up and so has the pace of construction. We’re glad to see so much cool stuff underway. Let’s have a look at the list!

  • Level 4: Flooring installed
  • Level 2 & 3: Cabinet installation underway
  • Elevator installation
  • Brickwork for street level on South first nearing completion
  • Stucco finish coat nearing completion
  • Lobby drywall complete
  • Lobby finishes underway

5/27/20

Willa’s construction schedule was delayed due to COVID-19. The City of Austin’s Shelter in Place ordinance temporarily shut down construction, followed by labor and material shortages. Scheduled construction completion (Temporary Certificate of Occupancy) for October 2020.

Despite the constraints in Q2, there was great progress achieved on site including: flat work / sidewalk along S 1st and Monroe – construction sidewalk removed. It looks excellent!

HVAC system on level 4 expected to be operational by end of June.

Up next: Cabinets, countertops, and flooring installation.